The Prompt Payment Act interest rate is the rate federal agencies must pay on late payments to contractors, set quarterly by the U.S. Treasury as the Treasury’s Current Value of Funds Rate (CVFR), generally a small percentage above the federal funds rate. In this guide, you’ll learn what that rate is, how it’s calculated, how to apply it to a late invoice, and what to do if a federal payment is late.
Formula
The interest owed on a late federal payment is calculated using simple interest, not compound interest. The formula is:
Interest = Principal × (Annual Rate / 100) × (Days Late / 365)
Where:
- Principal is the invoice amount (in dollars) that was paid late.
- Annual Rate is the Prompt Payment Act interest rate (in percent per year) in effect during the period of lateness.
- Days Late is the number of calendar days from the day after the payment due date to the date payment is actually made.
The rate is the Treasury’s Current Value of Funds Rate (CVFR), which is set quarterly and published in the Federal Register. It is essentially the government’s cost of borrowing, recalculated each quarter. For most federal contracts, the rate is the CVFR, but some contracts (e.g., those under certain statutes) may use a different rate, so always check the specific contract terms.
Worked Example
Using the default values from the calculator: an invoice of $10,000, an annual interest rate of 3.5%, and a payment that is 30 days late.
Step 1: Convert the annual rate to a decimal: 3.5% = 0.035.
Step 2: Calculate the daily interest rate: 0.035 / 365 = 0.00009589 (approximately).
Step 3: Multiply by the number of days late: 0.00009589 × 30 = 0.0028767.
Step 4: Multiply by the principal: $10,000 × 0.0028767 = $28.77.
So the interest due is $28.77, and the total amount the agency should pay is $10,028.77. The calculator rounds to the nearest cent, matching this result.
Assumptions
- The interest rate is fixed for the entire period of lateness (the rate in effect for each quarter is used, but for simplicity, the calculator uses a single rate).
- Interest is simple, not compounded.
- Days are counted as calendar days, not business days.
- The calculation does not include any other penalties, fees, or adjustments that might be specified in the contract or by law.
Background: What Is the Prompt Payment Act?
The Prompt Payment Act (31 U.S.C. § 3901-3907) was enacted in 1982 to require federal agencies to pay their invoices on time, or pay interest penalties if they are late. The act applies to most contracts for goods and services, as well as some grants and other agreements. The goal is to protect small businesses and other contractors from the financial strain of late federal payments.
The payment due date is generally 30 days after the agency receives a proper invoice, unless the contract specifies a different date. If the agency fails to pay by that date, it must automatically add the interest penalty to the next payment. The agency does not need to be asked; it is supposed to be automatic, though in practice contractors may need to request it.
How the Interest Rate Is Set
The Prompt Payment Act interest rate is set each quarter by the U.S. Treasury as the Current Value of Funds Rate (CVFR). This rate reflects the government’s average cost of borrowing for the previous quarter. For example, if the federal funds rate rises, the CVFR will likely rise as well. The rate is published in the Federal Register and on the Treasury’s website.
For most federal contracts, the CVFR is the applicable rate. However, some contracts may specify a different rate, such as the rate in the contract’s financing provisions or a rate set by a specific statute. Always check the contract’s payment clause to confirm which rate applies.
How to Use the Calculator
To estimate the interest on a late federal payment, enter the invoice amount, the annual interest rate (use the CVFR for the quarter in which the payment was late), and the number of days the payment was late. The calculator will show the interest due and the total amount that should be paid.
For example, if your invoice was $5,000, the rate was 4%, and the payment was 15 days late, the interest would be $5,000 × (4/100) × (15/365) = $8.22. That may seem small, but for large invoices and long delays, the interest can be significant.
Common Mistakes and Misconceptions
- Using the wrong rate: The rate changes quarterly. If a payment is late across multiple quarters, you must calculate interest using the rate for each quarter separately, not a single rate.
- Counting days incorrectly: The count starts the day after the due date, not on the due date itself. For example, if the due date is March 31 and payment is made April 10, the days late are 10 (April 1-10).
- Assuming compound interest: The act uses simple interest, so do not compound the interest.
- Forgetting to request the penalty: While the act says the agency should automatically pay the penalty, contractors often have to submit a separate invoice or request the interest payment. Keep records of when invoices were submitted and when payment was received.
What to Do If a Federal Payment Is Late
If a federal agency pays you late, you are entitled to interest, but you may need to take the following steps:
- Document the invoice submission date and the payment receipt date.
- Check the contract for the payment due date and any specific interest rate provisions.
- Calculate the interest using the CVFR for the relevant quarter(s).
- Contact the agency’s payment office to request the interest penalty. Be prepared to provide your calculation.
- If the agency does not respond, you can escalate to the agency’s dispute resolution office or file a claim under the Contract Disputes Act.
Keep in mind that the Prompt Payment Act also covers situations where a payment is late because the agency failed to pay within the required time, but it does not apply to disputes over the amount owed. If there is a genuine dispute, the interest clock may stop.
Frequently Asked Questions
What is the current Prompt Payment Act interest rate?
The rate changes quarterly. As of the third quarter of 2024, the CVFR was approximately 3.5%, but you should check the Treasury’s website or the Federal Register for the current rate. The rate is always published for each quarter, so you can use the rate that was in effect during the period of lateness.
How many days late before interest accrues?
Interest accrues from the day after the payment due date. The due date is typically 30 days after the agency receives a proper invoice, unless the contract says otherwise. There is no grace period; even one day late triggers interest.
Does the Prompt Payment Act apply to all federal contracts?
It applies to most contracts for goods and services, but there are exceptions. For example, it does not apply to contracts under the Federal Acquisition Regulation (FAR) that have their own payment clauses, or to certain grants and cooperative agreements. Check your contract to see if it references the Prompt Payment Act or has a specific payment clause.
Can I charge interest on late payments from state or local governments?
No, the Prompt Payment Act is federal law and applies only to federal agencies. Many states have their own prompt payment laws with different interest rates and rules. You would need to check the specific state law that applies to your contract.
What if the agency pays late but the invoice was defective?
If the invoice was not a proper invoice (e.g., missing required documentation), the agency may not be considered late. The interest clock only starts after the agency receives a proper invoice. If the agency rejects your invoice, you should correct it and resubmit, and the due date will start from the corrected invoice.
Is the interest penalty taxable?
Yes, interest income is generally taxable. You should report the interest as income on your tax return, just as you would with interest from a bank account. The agency will likely issue a 1099-INT form if the interest exceeds $10.
This calculator provides an estimate based on the general formula; the exact amount may vary if the rate changes during the period of lateness or if your contract specifies different terms. Always refer to the agency’s payment office or the contract itself for the precise calculation.
Related
Formula used
in p | Invoice amount | $ | 10000 | 0 | 100000000 in apr | Annual interest rate (CVFR) | % | 3.5 | 0.01 | 100 in days | Days late | days | 30 | 1 | 3650 out int | Interest due | $ | p * (apr / 100) * (days / 365) | 2 out total | Total due | $ | p + int | 2
Each line is one input (in, sel, list) or one result (out: label, unit, formula, decimals). How the calculators work
Method: the standard loan formula for this calculation, fixed rate and monthly compounding unless stated, rounded as each result states. Not financial advice; no lender, rate or product is recommended. See formulas and assumptions, the disclaimer or report an error.
More in this section
- Jet Fuel Cost per Gallon? Prices and What Affects Them
- High Amount Personal Loan Interest Rate Calculator$405.53
- Fuel Costs and Home Loans: How They Connect$405.53
- Fuel Costs Perth: Prices, Factors and Savings
- Car Quote for a Used-Car Trade-In: What It Means
- Cost of Fuel: Calculate Your Trip’s Fuel Expense$42.00